As Centrelink is one of our on-going clients we are required to meet their needs and complete the works over three weekends in two stages. The reason for this was to ensure that the existing occupants were not disturbed during the process.
The works included the installation of a new entry automated sliding glass door which created an air lock to the main entrance. The reconfiguration of existing workstations was a critical stage as we need to ensure that these were correctly positioned to where occupants had to work the next day.
Temporary timber stud framing with black plastic was put up to divide the space into the two stages. |